Scenario
A government contract is worth SAR 10 million. The entity requests additional work worth SAR 2.5 million, equivalent to 25% of the contract value.
Change order limits
An increase of up to 10% of the contract value. A reduction of up to 20% of the contract value.
Essential conditions
The work must fall within the scope of the contract. Funding must be available before approval. The official authorized to award the contract must issue the change order before execution and before acceptance of the contract work.
Ten cases and the applicable procedure
- 5% increase
- Permitted within the scope of the contract and the remaining limit, once the applicable conditions are met.
- 10% increase
- Permitted if the remaining limit allows it and the official authorized to award the contract issues a change order.
- 15% increase
- Exceeds the limit for increases by change order.
- Design work outside the contract scope
- If the need continues, use the appropriate procurement method under the applicable rules.
- Work carried out on verbal instructions
- Payment is not due for work outside the contract if it was performed without specific approval.
- Two increases of 6% and 5%
- The increases total 11%, exceeding the limit.
- 20% reduction
- Permitted to the extent justified by the actual need and the remaining limit, subject to the applicable conditions.
- 20% reduction followed by a request for a 15% increase
- Savings from a reduction do not raise the limit for increases.
- Additional work requiring an extension
- The official authorized to award the contract approves a period proportionate to the volume and nature of the work and the date it was assigned.
- Essential work exceeding 10%
- Assess whether the work can be separated. Use the appropriate procurement method for work that cannot be included in the contract.
Bottom line
The increase limit in this example is SAR 1 million. The procurement and contracts department reviews the scope, total change orders and budget allocation.
References in the original
Government Tenders and Procurement Law, Articles 69 and 74. Implementing Regulations, Articles 114, 115 and 125(4).