A technically compliant bid may be priced well below the estimate and prevailing market prices. The evaluation committee must examine the bid under the applicable procurement rules.

Worked example

A government entity estimates a tender at SAR 10 million. It receives three bids.

Bid 1: SAR 7.5 million | Bid 2: SAR 9.4 million | Bid 3: SAR 9.8 million

The first bid is 25% below the estimate. The example gives no market benchmark. Check prevailing prices separately.

The 25% threshold

Article 48 of the Government Tenders and Procurement Law (1440 AH) addresses bids at least 25% below both the cost estimate and prevailing market prices. Reaching the threshold does not automatically disqualify the bid.

Review the estimated prices, discuss the bid with the bidder, and request a written breakdown of its price components and an explanation for the low price. Assess the bidder’s ability to deliver. If the committee remains unconvinced, it may recommend exclusion.

Article 84 of the Implementing Regulations

Consider the bidder’s capability, including any prior qualification or technical evaluation. Take account of the nature of the work and whether the low price would affect delivery.

How to handle the bid at each stage

Before award. Analyse the bid and the reasons for its low price. Check the realism of the prices and the bidder’s ability to perform.

After award, before signature. Review the evaluation and award procedures. Address any material defect under the applicable rules.

After signature. Monitor performance and address difficulties or breaches under the contract and the law. A low price alone is not grounds to amend or terminate the contract.

Six practical lessons

1. Do not exclude a bid solely because its price is low.

2. Verify the cost estimate and prevailing market prices.

3. Analyse the prices of key items as well as the total bid.

4. Request evidence of the bidder’s ability to deliver.

5. Document the reasons for acceptance or for recommending exclusion.

6. Weigh the potential savings against delivery risks.

Conclusion

Examine the price and the bidder’s capacity to perform before deciding. This protects both value for money and successful delivery.