What to Do When a Supplier's Bid Price in Figures Differs from the Price in Words

English transcript
Practical scenario
After opening financial bids in a government tender, the committee discovers two different prices in a supplier's bid. In figures: SAR 1,250,000. In words: one million two hundred and five thousand riyals (SAR 1,205,000). The difference is SAR 45,000. Opinions may differ: use the words, use the lower price to save money, or ask the supplier to specify the correct price. What is the appropriate procedure?
Key concepts
Price correction: correcting a financial bid error according to defined statutory rules without allowing the supplier to submit a new price. Price amendment: changing the submitted price after opening bids; this is not permissible merely because an error or changed calculations are discovered.
1 — Figures differ from words
Apply the price written in words under the statutory correction rule, subject to relevant controls and exceptions.
2 — Error in adding item prices
Review and correct the arithmetic in accordance with approved rules.
3 — Unit price differs from item total
Apply the rules for correcting unit prices and totals.
4 — Two prices for the same item
Review the nature of the discrepancy and determine the appropriate action under tender documents.
5 — Supplier requests price increase after bid opening
No bid amendment is permitted outside statutory correction procedures.
6 — Correction changes suppliers' rankings
Re-rank bids based on corrected prices and evaluation criteria.
7 — Error is large and significantly affects bid value
Check the permitted correction limits and effect on acceptance of the bid.
8 — Supplier rejects corrected price
Verify the accuracy of the correction and apply the prescribed statutory consequences.
General correction rules
Follow statutory correction requirements and tender documents. Do not choose the lowest price simply because it is cheaper. Re-rank bids if correction affects outcomes. Record the correction and justification in committee minutes. Verify whether correction affects evaluation and acceptance.
Legal reference
Government Tenders and Procurement Law, its Implementing Regulations and the tender documents.
Summary
If a supplier writes one price in figures and another in words, use the price written in words according to the statutory correction rule, taking into account relevant provisions and exceptions.
Reference note
English edition of the Arabic educational infographic. Unless explicitly identified as verified, legal citations and figures are those of the original source and may reflect its publication date. Check the applicable official text and transitional provisions before relying on them.