When a contractor follows consultant instructions that conflict with the contract

↓ Download
When a contractor follows consultant instructions that conflict with the contract. An accessible transcript follows.

When are the instructions binding, and who bears responsibility?

Scenario

The consultant instructed the contractor to change materials, the method of execution or certain specifications. The contractor followed the instructions. The entity later found that they conflicted with the project contract and approved specifications and had been issued without the required approval.

Changes to materials and specifications

1. Changing a specified material: verify that the substitute meets requirements, obtain approval and complete the contract amendment process where needed.

2. Additional work under verbal instructions: document the instruction, check approval authority and address the work under approved change procedures.

3. Approval of inferior material: address nonconformity, correct the work and determine responsibility under the contract.

Changes to the method of execution

4. Changing the method without changing specifications: check whether the contract allows it and assess the impact on quality, duration and cost.

5. Contractor objects but proceeds: review the reasons, verify the validity of the instruction and determine responsibility.

6. Nonconforming work is approved but later rejected by the acceptance committee: correct the work and review the consultant’s responsibility for approving it.

Duration, cost and resources

7. Work stops on the consultant’s instructions: check the authority to suspend work and its effect on duration and costs, then act under the contract.

8. Acceleration with more labor and equipment: determine whether it falls within existing obligations or requires an amendment, and address time or cost impacts.

9. A change is recorded in minutes attended by the consultant and the entity’s representative: verify change approvals and complete the contractual procedures.

Acceptance, warranties and contractual compliance

10. New work outside the contract: verify whether it was separately contracted or can be treated as a change order, and obtain the required approval.

11. Nonconformity is discovered after acceptance and final acceptance: distinguish apparent from latent defects, apply warranty terms and address contractual consequences.

12. Contractor and consultant interpret requirements differently: refer to the contract, approved specifications and drawings, and seek the competent authority’s opinion as needed.

Responsibilities

Contractor: execute according to the contract and specifications, verify each instruction and its authority, and do not rely solely on verbal instructions.

Consultant: issue instructions within approved powers, check conformity with the contract and specifications, and bear responsibility for exceeding authority or approving nonconforming work.

Government entity: approve consequential changes under the contract, oversee instructions and completed work, address noncompliance and determine responsibility.

Bottom line

Consultant instructions are not automatically binding. Changes to specifications, scope, duration or cost require the entity’s approval and the contract amendment procedures.

Responsibility depends on each party’s authority and role in the noncompliance. Record all instructions and approvals in approved minutes.

References in the original

Government Tenders and Procurement Law and its Implementing Regulations, contract terms, and provisions on contract amendments, supervision and acceptance.