Contracts · Committees
Reducing the Contract Scope or Omitting Contract Items?
Does the 20% Limit Allow a Government Entity to Omit Any Work?

Practical Scenario
- A government entity signed a SAR 10 million contract to supply, install and commission equipment.
- After work began, the entity decided to omit work valued at SAR 1.5 million, or 15% of the contract value.
- The proposed omissions included commissioning and systems integration, both essential to the project’s intended outcome.
Contract value: SAR 10 million; Proposed omission: SAR 1.5 million; Reduction: 15%.
Comparing the Two Approaches
Reducing Obligations
- Reduces the volume of work or quantities for some items.
- Reflects the government entity’s actual needs.
- Preserves the nature of the contract and serves its purpose.
Omitting Contract Items
- Removes an entire contracted item.
- May affect the nature of the contract or the purpose of the project.
- Requires a careful technical and contractual assessment.
Steps for a Sound Decision
- Verify the actual need for a reduction.
- Identify the work proposed for omission and assess its impact.
- Assess the effect on the nature of the contract and its financial balance.
- Assess the effect on the contract term and remaining obligations.
- Secure the approvals and have the competent authority issue the change order.
Key Points
- 20% is a ceiling for reductions, not automatic approval to omit any work.
- Omitting a whole item calls for reviewing its effect on the contract.
- The change must preserve the nature of the contract and its financial balance.
- A reduction decision needs clear justification and formal documentation.
Legal Basis
- Law, Article 69
- A government entity may issue reduction change orders, within its actual needs and up to 20% of the contract value, subject to the regulations.
- Implementing Regulations, Article 114(2)
- Changes must serve the entity’s interests without compromising terms or specifications, changing the scope or nature of the contract, or disturbing its financial balance.
- Implementing Regulations, Article 114(7)
- The official with award authority issues orders increasing or reducing the contractor’s obligations.
Key Takeaway
A compliant change order depends on three things: the statutory limit, the nature of the work, and its impact on the project.
Author: Ibrahim Alhumaid.