Reducing the Contract Scope or Omitting Contract Items?

Does the 20% Limit Allow a Government Entity to Omit Any Work?

Download
Reducing the Contract Scope or Omitting Contract Items?

Practical Scenario

Contract value: SAR 10 million; Proposed omission: SAR 1.5 million; Reduction: 15%.

Comparing the Two Approaches

Reducing Obligations

Omitting Contract Items

Steps for a Sound Decision

  1. Verify the actual need for a reduction.
  2. Identify the work proposed for omission and assess its impact.
  3. Assess the effect on the nature of the contract and its financial balance.
  4. Assess the effect on the contract term and remaining obligations.
  5. Secure the approvals and have the competent authority issue the change order.

Key Points

Legal Basis

Law, Article 69
A government entity may issue reduction change orders, within its actual needs and up to 20% of the contract value, subject to the regulations.
Implementing Regulations, Article 114(2)
Changes must serve the entity’s interests without compromising terms or specifications, changing the scope or nature of the contract, or disturbing its financial balance.
Implementing Regulations, Article 114(7)
The official with award authority issues orders increasing or reducing the contractor’s obligations.

Key Takeaway

A compliant change order depends on three things: the statutory limit, the nature of the work, and its impact on the project.

Author: Ibrahim Alhumaid.