When the Contract Conflicts with the Tender Specifications

The tender says two years; the contract says one. How do you resolve it?

Practical case

The tender specifies two years of maintenance, but the signed contract says one year. Neither the date of the contract nor the fact that a requirement was in the tender settles the conflict on its own.

Six steps for resolving the conflict

  1. Identify the conflict. Record the exact contract and tender clauses that differ.
  2. Review the contract documents. Check the signed contract, tender specifications, accepted bid, award letter and all annexes.
  3. Check the order of precedence. Use the contractual clause to identify which incorporated document takes priority.
  4. Assess technical and financial impact. Review how the difference affects the scope, price, duration and obligations.
  5. Identify the right remedy. Consider the nature and effect of the conflict under the applicable law and regulations.
  6. Decide and document. Obtain the decision from the competent authority, record the reasons, notify the contractor and update the documents if required.

Three possible routes

Apply the document that takes precedence

Where the precedence clause resolves the inconsistency, apply the controlling document after checking conformity with the applicable law and regulations.

Interpret an existing obligation

If the language is ambiguous, read the relevant documents together and seek technical and legal input. Do not use interpretation to add a new obligation.

Amend the contract where permitted

If the proposed solution changes the work, scope, obligations or price, identify the specific authority and approvals required. For changes to contracted works, check Law Article 69 and amended Regulation Article 114 where applicable. A price adjustment is not automatically a change order.

What can be affected?

Regulatory references

These citations concern the Saudi Government Tenders and Procurement Law under Royal Decree M/128 and its implementing regulations. Apply the relevant transitional rules.

Law and implementing regulations · Article 114 amendment · Transitional provisions

Bottom line

Start with document precedence and the actual wording. Then decide whether you are clarifying an existing obligation or proposing a new contractual change.