Can a contractor be required to carry out work not explicitly listed in the contract?

What falls within the contract scope, and when does additional work require a change order?
Contract scope
A contractor's obligations are defined by the scope and documents of the contract. Work outside that scope becomes binding only through the applicable formal procedure.
What falls within scope?
Work specified in the contract and its documents.
Work further defined by the specifications, drawings and bills of quantities.
Complementary work needed to deliver the same agreed output.
When might work be treated as additional?
Quantities increase or the scope changes materially.
New items or outputs are added.
Specifications change in a way that increases cost or affects duration.
The request is verbal or falls outside the contract documents.
What should you do?
Review the scope and contract documents.
Determine whether the work falls within scope.
If it falls outside scope, submit it as a change order request.
Document and obtain approval for the amendment before undertaking the work.
Bottom line
Review the full scope and contract documents. Additional work needs a legal basis and a formal procedure.
References in the original
Government Tenders and Procurement Law, Article 69. Implementing Regulations, Articles 114 and 115.