Can Prior Qualification Be Used When a New Tender Requires a Higher Contractor Classification?

English transcript
Scenario
A contractor qualified for a government project six months ago with third-grade classification. The contractor submits a bid for a new tender requiring first-grade classification and asks: I was qualified before, and less than a year has passed — why qualify me again?
Cases 1–3
1. First-grade contractor; tender requires first grade: accept the classification, subject to verification of all other requirements. 2. Second grade; tender requires first grade: lower classification cannot substitute for the required grade. 3. Third grade; tender requires first grade: the required classification is not met.
Cases 4–6
4. First grade; tender requires second grade: a higher classification may be accepted, taking into account field, activity and statutory limits. 5. Second grade; tender requires third grade: higher classification may be accepted if all other requirements are met. 6. Third grade; tender requires third grade: grade requirement satisfied; review other qualification criteria.
Cases 7–9
7. Fourth grade; tender requires second grade: required classification is not met. 8. First grade, but in a different field: a higher grade alone is insufficient; classification must cover the project field and activity. 9. Qualified six months ago, but classification certificate has expired: valid classification satisfying requirements is necessary.
Cases 10–12
10. Classification upgraded from third to first grade: verify the updated classification certificate and apply tender requirements. 11. Prior qualification and similar new works: use prior qualification subject to applicable controls, but it does not exempt the contractor from the required classification grade. 12. Second grade; contractor bids in a consortium for a first-grade project: review consortium requirements, since special provisions govern the classification grades of consortium members.
Important distinction
Contractor classification is a grade issued by the competent authority specifying the field, activity and grade (first, second, third, etc.). Contractor qualification is an assessment conducted by the government entity to verify that the tender-specific qualification criteria are met.
Legal references
Contractors Classification Law, Article 3; Article 9 on consortium arrangements; Implementing Regulations of the Contractors Classification Law; Government Tenders and Procurement Law and its Implementing Regulations.
Summary
If a contractor qualified six months ago with third-grade classification but the new tender requires first grade, prior qualification cannot bypass the classification requirement. Less than one year since prior qualification does not automatically raise the contractor's classification grade, nor is prior qualification automatically invalidated solely because the new tender requirements are not met.