Category: Contracts
Criteria for Replacing a Contractor in Government Tenders

English transcript
Purpose
The grounds for changing a contractor, impacts, procedures and parties vary with contract type. Replacing a contractor is not an easy decision but a regulatory and institutional procedure based on clear reasons, specific impacts and comprehensive assessment, ensuring continuity of work and protection of the public interest.
1. When does replacement become necessary?
Serious regulatory violation: fraud, bribery, manipulation, liquidation, insolvency or unauthorized assignment; e.g. proof of corruption, court rulings or contractor bankruptcy.
Material contractual breach: delay or default in performance, failure to correct after warning, unauthorized subcontracting; e.g. delayed schedules or noncompliance with specifications.
Partial withdrawal: breach in a specific part of the works and failure to remedy after notice; e.g. stalled implementation of a specified component.
Public interest: valid reasons under regulatory requirements and approvals; e.g. changed priorities or needs.
Termination by agreement: parties agree to terminate; amicable settlement of obligations.
Natural expiry: term expires or works are completed; e.g. end of contract term.
Remediable poor performance: low quality, repeated observations or failure to achieve service levels; service level below requirement.
2. Contract type — reasons, potential impact and appropriate measure
Construction and public works: stopped work, poor output, defects or schedule noncompliance; delay, cost increases and safety risks; end, partially withdraw or re-contract.
Operation and maintenance: repeated breakdowns, poor maintenance or service-level noncompliance; facility disruption and reduced efficiency; remedy, partial withdrawal or termination.
Supply: late delivery, nonconformity or missing quantities; shortages or work disruption; re-contract or partial withdrawal.
Consulting: poor deliverables, delay or unmet requirements; delayed decisions or rework; remedy, termination or re-contracting.
IT: technical requirement breach, weak support or project failure; system disruption and security risks; re-contract or partial withdrawal.
Continuous services: service noncompliance, resource shortage or repeated performance indicators breach; beneficiary impact and lower service quality; remedy, termination or re-contracting.
Training: poor performance or failure to satisfy content or outputs; delays or repeated work; remedy, termination or re-contracting.
3. Business continuity impacts
Operational: service interruption or reduced efficiency.
Financial: increased cost of remediation and re-performance.
Technical: material defects or repeated failures.
Timing: delays affecting interrelated phases or projects.
Regulatory: grounds falling within statutory termination cases.
Security and safety: risks to persons or facilities.
Contractual: breach of material conditions despite notification.
Strategic: need for the works ends or their feasibility changes.
4. Stakeholders and responsibilities
Beneficiary department: detect performance deficiencies and assess impact on services and beneficiaries.
Project manager/supervisor: monitor implementation, document observations and delays.
Technical department: assess work quality and scope of default.
Procurement and contracts department: review contractual obligations and prepare subsequent procurement route.
Legal department: assess regulatory basis, termination risks and claims.
Finance department: review entitlements, cost and available appropriation.
Risk management: assess business-continuity risks.
Competent committee: assess matter and provide recommendation where prescribed.
Authorized decision-maker: approve decision under delegated authority and controls.
Oversight entities: approvals or notification as applicable to jurisdiction.
5. Compare available alternatives
Remedy default: remediable breach; return implementation to the correct course; contractor continues; document observations, warnings and corrective plan; penalties and obligations according to contract; least operational disruption.
Partial withdrawal: a part of the work; complete affected portion; contractor continues non-withdrawn work; establish breach and scope of withdrawn work; perform withdrawn portion at contractor’s expense; requires coordination.
Contract termination: entire contractual relationship; address situation requiring termination; contractor’s relationship ends; establish regulatory basis and complete procedures; settle entitlements; may require an alternative plan.
6. Institutional decision process
1. Detect default — contract supervisor or beneficiary entity.
2. Document and analyze — technical department and contracts.
3. Legal and financial assessment — legal and financial departments.
4. Study alternatives — remedy, partial withdrawal or termination.
5. Recommendation and approval — competent committee when required, then authorized decision-maker.
6. Implement decision — remedy default, arrange settlement and implement transition plan.
7. Contractor change decision evaluation criteria
Workforce/alternative readiness; regulatory basis; risk; service continuity; potential for remediation; time; total cost; document quality.
8. Requirements for transition to a new contractor
1. Inventory completed and outstanding works.
2. Document defects, observations and claims.
3. Determine entitlements and guarantees.
4. Receive sites, data and licenses.
5. Prepare business continuity plan.
6. Define future scope of works.
7. Select the appropriate contracting method.
8. Transfer knowledge and documents.
9. Define contractors’ responsibilities.
10. Document handover and close out obligations.
9. Important cautions
Not every performance deficiency in a contract is an independent ground for termination. The entity’s desire to perform the work itself or through another contractor is not sufficient reason to terminate the contract. Responsibilities and procedures differ according to the contract type and the entity’s organizational structure. A decision to change the contractor should be based on objective assessment of impacts, risks and costs. Ensuring business continuity and quality of deliverables is the main objective of the decision.
Reference note
English edition of the Arabic educational infographic. Unless explicitly identified as verified, legal citations and figures are those of the original source and may reflect its publication date. Check the applicable official text and transitional provisions before relying on them.