Incorrect quantities after award: amend the contract or re-tender?

Download
Incorrect quantities after award: amend the contract or re-tender?

What if the correct quantities would have changed the winning bid?

Who bears the consequences? A public entity may issue a tender using its own bill of quantities, then discover after award or signature that some estimates are substantially above or below actual needs. Is this a quantity adjustment or a material error affecting prices and the tender outcome?

Four questions before deciding

1. Cause: Was there a measurement error, a discrepancy in the drawings or a new requirement?

2. Competition: Could the difference affect bid prices or rankings?

3. Contract: Does the increase or reduction fall within the contracted scope? What are the cost and schedule implications?

4. Applicable procedure: Can the discrepancy be addressed under the contract and applicable rules, or is another formal procedure required?

Why the discrepancy matters

Contract price: Bidders priced the published quantities. Their prices might have differed had the correct quantities been known.

Tender outcome: One bidder may have priced a low-volume item cheaply while another quoted a higher unit price for the same item.

Economic balance: A large increase can raise costs and change the assumptions behind the price.

Procedural integrity: The response depends on the contract type, the work, applicable limits, delegated authority and required procedures.

Choose the response for the contract stage

After award, before signature: Assess the effect on project scope and on the basis of competition. A material error that cannot be remedied may require cancellation and re-tendering under the applicable rules.

After signature: Assess any increase or reduction under the applicable provisions. Examine its cost and schedule implications and the authority granted by the law and the contract.

Six lessons for procurement teams

1. Have the bill of quantities independently reviewed before approval.

2. Look beyond the percentage change in quantities.

3. Test how the discrepancy affects bid rankings.

4. Consider alternatives before using a change order.

5. Record the reasons for the discrepancy and the decision taken.

6. Use errors discovered to put preventive checks in place.

Takeaway

A sound tender starts with an accurate statement of need and a reliable quantity takeoff. An error in preparation can become a contractual, financial and regulatory problem even when tendering and award procedures are properly followed.

Prevent quantity discrepancies before issuing the tender, as well as planning how to address them when discovered.