Government Tenders Above SAR 25 Million: Is the Entity’s Approval Enough to Launch?

Approval and review
Internal approval does not by itself satisfy the launch requirements. Tenders above SAR 25 million are subject to pre-launch review by the Expenditure and Projects Efficiency Authority under the applicable rules and instructions.
Above SAR 25 million
Submit the tender to the Authority before launch for review of the feasibility study, cost estimate and tender documents.
SAR 25 million or less
Notify the Authority as required by the approved channels and applicable exceptions. The Authority may request review in particular cases under specified rules.
Review period
Where review is required, allow 15 working days from receipt of the complete documentation.
What the two approvals address
The entity considers operational need, the approved appropriation and alignment with objectives and priorities. The Authority considers economic feasibility, duplication of expenditure and compliance with applicable rules and instructions.
Possible reasons for withholding approval
1. Similar ongoing public projects or initiatives. 2. An existing contract can cover the need. 3. Weak economic feasibility. 4. An inflated estimate without adequate study or justification. 5. Unclear or overlapping scope. 6. Quantities exceeding actual need. 7. Similar projects can be combined to reduce duplication and generate savings. 8. Weak justification for launch because the project is not linked to approved strategic objectives or priorities.
Effects of withholding approval
The launch does not proceed. The project may be deferred or reassessed. The scope or specifications may need to be amended, the project may be combined with others, or lower-cost alternatives may be explored.
Proposed response
1. Obtain the reasons for withholding approval and the legal basis. 2. Confirm the applicable scope of the Authority’s jurisdiction and review requirements. 3. Compare current contracts with the proposed project. 4. Establish the need and document gaps the current contracts do not cover. 5. Update the feasibility study, cost estimate and alternatives. 6. Request reconsideration through official channels. 7. Present the findings and options to the authorized official for decision.
Outcome
Efficient spending requires reviewing projects for duplicate or excessive costs, completing the applicable approvals, and balancing actual need, economic feasibility and oversight.
Sources and notes
Government Tenders and Procurement Law, Article 15. Implementing Regulations, Article 7. Review requirements may differ by project type and nature. Consult the Authority’s latest instructions, document the steps and communicate through approved channels.