Signs of Tender Splitting

Eight signs to examine
1. Similar scope across several related consulting requests. 2. Tender dates clustered in a short period. 3. Multiple requests for the same type of service from one requesting department. 4. Estimates close to financial thresholds that affect procedures or authority. 5. Similar awards repeatedly going to one supplier without clear reasons. 6. Related consulting services for one project split even though they could be combined. 7. Repeated urgent requests for predictable services. 8. Similar specifications or locations for the same entity or sites without clear justification.
When separate tenders may be justified
Services differ in nature. The requesting department or project scope differs. Timing differs because of an actual need. Technical requirements warrant independent tenders. Documented reasons make combining them impractical.
When splitting becomes a violation
Breaking up one need to bypass formal procedures. Reducing values to reach the direct purchase threshold or a particular approval level. Soliciting similar consulting services for the same entity without genuine justification. Ignoring the link between activities or phases of the project. Failing to document the reasons for separation.
Role of Procurement and Contracts before solicitation
Review requests with the requesting entity. Check the procurement plan and estimated needs. Coordinate with technical teams to assess bundling.
During solicitation
Review the scope, specifications and estimated values. Verify that splitting is not used to bypass procedures or authority. Check for links among tenders for the same entity or project.
After award
Analyze similar contracts and recurring suppliers. Track repeated services and consider combining future purchases. Report indicators to the competent authorities when needed.
Example: four consulting tenders in three months
A government entity intends to prepare a digital transformation strategy. Tender 1: current-state assessment, SAR 295,000. Tender 2: digital roadmap, SAR 300,000. Tender 3: performance indicator design, SAR 290,000. Tender 4: digital governance model, SAR 280,000.
What warrants scrutiny in the example
All services relate to one digital transformation project. Tender dates are close, scopes overlap, estimates are similar, and the same department requested all four. Examine whether they can be combined into a single tender or structured as phases in one integrated contract, or document why they need to be separate.
Summary
Look beyond the number of requests. Examine how the needs relate, when they were requested, why they were separated and which procedures resulted.