When Do Repeated Change Orders Amount to an Unadvertised New Tender?

Why it matters
Change orders address developments during performance. Repeated changes or their cumulative value can materially alter the scope and effectively create a new project that should have been tendered separately.
What a change order may cover
Changes to scope or method of performance, a time extension, increases or decreases in quantities, and revisions to technical requirements.
When a change order is justified
A real need arises after award. The change stays within the original scope and objectives, has documented technical and financial justification, follows approved procedures and authority, preserves the essential nature of the contract and stays within the legal limits on amendments.
Four typical changes
Limited amendments to specifications or technical details. Quantity increases or decreases within the same scope. Time extensions for circumstances outside the parties’ control. Changes in method without changing the contract’s objectives.
Four signs a new tender may be needed
Repeated changes cause a large increase over the original contract value. Changes alter the project’s nature or underlying system. New works were absent from the tender documents. The cumulative effect compromises competition, fairness or equal opportunity.
Controls
Review changes and their cumulative impact periodically. Compare aggregate change value with the original contract. Confirm the work stays within the original scope. Coordinate early with Legal and Finance. Document technical and financial grounds for every change. Preserve fairness and equal opportunity and avoid circumventing competition.
Responsibilities
The requesting department defines the actual need and justifies it technically. Procurement and Contracts checks compliance and the change’s effect on the nature of the contract. Legal evaluates legal risks and advises. Finance reviews the financial impact and verifies availability of funds.
Examples and decision
Large and repeated increases in contract value, a major change in the nature of the project, or adding work outside the original contract may call for a new tender. Consider a new tender when repeated amendments materially change scope, value or objectives. This supports the public interest, legal compliance, spending efficiency, sound change management and fair competition.