When Does the Contract Period Start for Government Projects?

Commencement record, site handover or an agreed start and end date
Three ways to record commencement
- Commencement record: records the contractor’s actual start after contractual requirements are completed. Time runs from the approved date where the contract provides for this.
- Site handover record: confirms that all or part of the site is handed over and ready. Time runs from that date where the contract makes site handover the trigger.
- Specified dates: the contract or tender documents set a start date and an agreed end date. Observe the dates stated in the contract.
Which approach fits?
- A commencement record records actual mobilization and may apply to projects or services that require preparatory steps. It may involve a physical site or may not.
- A site handover record concerns projects tied to a site, especially construction and site work. It triggers the contract period if the contract says so.
- Fixed dates are a specific contractual arrangement and may suit services, operations or maintenance. The link to a site depends on the contract.
Valid commencement • Cases 1–4
- 1. Sign a commencement record after contractual requirements are complete. Use the approved date and monitor the schedule.
- 2. Hand over the site through formal minutes when it is ready for execution. Calculate the period from handover as the contract provides.
- 3. Start a service on the date stated in the contract. Observe the agreed start and end dates.
- 4. Deliver in stages, with an approved start for each stage. Record each date and monitor the delivery program.
Conditional situations • Cases 5–8
- 5. Sign a commencement record while requirements remain incomplete. Complete the requirements before actual performance.
- 6. Hand over a site containing obstacles or unready areas. Record reservations in the minutes and resolve the obstacles before starting the affected work.
- 7. The specified start date arrives but the site is unready. Record the cause of delay and apply the appropriate extension or suspension procedure.
- 8. A contractor delays accepting a site that has been formally handed over. Give notice, apply the prescribed procedure and consider the rules on deemed handover.
Noncompliant situations • Cases 9–12
- 9. Start work before contract signature without a lawful exception. Stop the unauthorized start and complete the required process.
- 10. Treat the award date as the commencement date without a contractual basis. Use the trigger specified in the contract.
- 11. Alter the start or end date administratively without the prescribed approval. Follow the procedure for changing the period.
- 12. Backdate a commencement record when no actual start occurred. Record the true start date and avoid inaccurate statements.
Procurement and contracts responsibilities
- Reconcile the contract period and commencement method. Check site readiness and handover steps, minutes and dates. Monitor the delivery program and end date. Handle any requested extension under the applicable rules.
- Key risks: parties disagreeing on dates, a partially ready site, contractor delay in mobilizing, unsupported changes to time, and difficulties assessing delays or claims.
Summary and references
- Use the commencement trigger set by the contract and record it properly. The reference framework is the Government Tenders and Procurement Law, its Implementing Regulations and approved contract models.
- Under the 1440 AH framework, Implementing Regulations Article 88 requires signature before commencement, subject to Law Article 55(2). Verify which law and contract govern the project.