How Does a Government Contract Begin?

Commencement methods and practical situations. Does the contract start on signature, a commencement record, site handover or a specified date?
Signature: Starts on signing unless otherwise agreed. Commencement record: Starts on the approved date recorded by both parties. Site handover: Starts on the handover record date when the site is ready and execution requirements are met. Specified date: Starts on the date expressly agreed, including after a period or on meeting a condition.
Illustrative suitability (the actual contract governs): Construction and projects: commencement record, site handover or specified date. Supplies, equipment, IT, general services, consultancy and design: signature, commencement record or specified date. Operations and maintenance: all four methods may suit; site or facility handover may be required before operations begin.
Fully ready: Issue the commencement record and calculate the period. Site handover needed: Complete and officially document handover and readiness. Entity delays preparation: Adjust the schedule under approved contract terms and circumstances. Partial commencement: Permit a defined part of the scope under an approved partial agreement. Specified start: Follow the contract date even if other records are issued.
Procurement and contracts: Select the suitable method and align it with tender documents and contract; verify site, permits and equipment readiness before approving commencement; monitor and update the period and maintain approved indicators.