Terminating a Government Contract in the Public Interest
Government entities sometimes cite the public interest when considering whether to end a contract before completion. This post explains when that ground may apply, and what should be documented before a decision is made.
What does the legal framework say?
The Arabic infographic refers to Article 77 of the Saudi Government Tenders and Procurement Law and Article 132 of its Implementing Regulations. An entity’s mere preference to end a contract, carry out the work itself or switch to another contractor does not, by itself, establish a public-interest ground.
Four situations illustrated in the Arabic design
- Security or safety. Continuing the contract would harm security, health, public safety or the environment.
- Work of another government entity. Continuing the contract would interfere with another government entity’s work.
- Exceptional circumstances. Circumstances beyond the entity’s control prevent it from continuing the contract.
- The need has ceased. There is no actual need to complete the work or services, based on a technical recommendation establishing that continuation is not worthwhile.
Procedural safeguards described in the design
- Document objective grounds and retain the supporting evidence, taking account of the requirements applicable to the case.
- For cases outside the four examples, the design describes submitting a reasoned request to the Ministry of Finance, which decides on the request within the period set by the regulations. Article 77 addresses Ministry approval. Check the applicable regulatory text before treating the examples as exceptions.
- The design describes a decision by the authorized official on the recommendation of the bid evaluation committee and notification to the General Court of Audit.
- Notify the contractor. The Arabic image gives a period of 20 working days. The published consolidated text of Article 132 cited below instead states that termination takes effect 30 days after the contractor is notified. Use the official text applicable to the contract for this deadline.
- Do not rely on the public interest solely because the entity wishes to perform the work itself or use another contractor.
Summary
Public-interest termination requires a substantiated ground and compliance with the applicable controls and procedures.