01 · Sound, complete recommendation
Approve the recommendation and decide on the award in accordance with the statutory procedures.
02 · Error in bid evaluation
Hold approval. Identify the error, assess its effect, and correct it through the applicable procedure.
03 · Technical team disagrees
Review the reasons for the disagreement and confirm that the approved evaluation criteria were applied.
04 · Preference for a different company
Personal preference gives no basis for changing the evaluation outcome.
05 · Another bid is cheaper
Apply the evaluation criteria published in the tender documents. The lowest price does not always identify the best bid.
06 · Incomplete committee minutes
Complete the supporting reasons and documentation before deciding on the award.
07 · Requesting department objects
Review the department’s comments. Its view alone does not change the evaluation result.
08 · Correctable irregularity
Correct the irregularity through the applicable procedure and review its impact on the tender result.
09 · Material, uncorrectable irregularity
Hold approval of the recommendation. Assess whether a statutory ground for cancelling the tender applies.
10 · Need remains after cancellation
Address the reasons for cancellation. Run a new tender in accordance with the applicable procedures.
What the three options mean
Declining the recommendation
Withhold approval of the current recommendation for a documented reason and follow the applicable procedure.
Cancelling the tender
End the tender in the cases and under the conditions set by law.
Re-tendering
Issue a new tender after addressing the reasons for cancellation.
Summary
How to decide
Review each recommendation on its merits. Determine whether an error can be corrected before considering cancellation. Apply the published criteria when deciding which bid should win.
Legal reference · Article 45 of the Saudi Government Tenders and Procurement Law covers the Bid Examination Committee, the record of its recommendations, and the approving authority’s award decision. The Arabic design cites Articles 43, 44 and 48. Article 51 sets the grounds for cancelling the tender. Official text of the law