The committee negotiated with the supplier, then the budget was adjusted.

The case

1. Approved project budget: SAR 5 million. Best compliant bid: SAR 6 million.

2. The supplier was asked to reduce the price to SAR 5 million. It agreed to a SAR 100,000 reduction, bringing its bid to SAR 5.9 million.

3. An additional SAR 900,000 was secured and the budget was adjusted during bid evaluation.

4. The committee recommended award at SAR 5.9 million before completing negotiations with the remaining bidders.

Procedure described in Article 47(2)

1. Negotiate with the best bidder and request a reduction to the approved amount.

2. Move to the next bid if the first bidder does not reach the required price.

3. If negotiations fail, reduce items or quantities subject to the applicable rules and without impairing the project’s intended use.

4. Cancel the tender if the approved amount cannot be reached.

Assessment in the original

The committee did not complete the prescribed procedure. The reduced bid of SAR 5.9 million was still above the SAR 5 million approved when negotiations took place.

The committee recommended award after the budget adjustment without completing negotiations with the remaining bidders.

Adjusting the budget during bid evaluation is not an alternative provided in Article 47(2).

Recommended action

1. Pause approval of the award recommendation pending a compliance review.

2. Re-examine the bid evaluation committee minutes and verify the outcome of negotiations with the supplier.

3. Check when the additional funding was approved and how the budget adjustment affects the negotiation process.

4. Complete the prescribed steps, including negotiating with the remaining bidders when required, then refer the recommendation to the authority empowered to decide the award.

References in the original

Government Tenders and Procurement Law, Article 47(2). Implementing Regulations, Article 83.