After opening the bids, the committee finds that some tender requirements appear too strict or too lenient. Members propose raising or lowering them.
The applicable procedure
The Bid Evaluation Committee has no authority to amend tender requirements after bid opening.
If the committee identifies a material defect that affects the integrity of the tender, it documents its findings and their impact and submits a reasoned recommendation to cancel the tender if statutory grounds exist.
The decision to cancel rests with the authorized decision-maker.
Examples of proposed changes
Years of experience: The tender requires 10 years. Proposed increase to 15 years or reduction to 5 years.
Previous projects: The tender requires 5 similar projects. Proposed increase to 8 projects or reduction to 3 projects.
Technical staff: The tender requires 5 specialists. Proposed increase to 10 specialists or reduction to 3 specialists.
Evaluation criteria: Experience accounts for 20%. Proposed increase to 40% or reduction to 10%.
Summary
The Bid Evaluation Committee has no authority to raise or lower tender requirements after bid opening.
Reference
Government Tenders and Procurement Law and its Implementing Regulations.