Local content
Won the tender on local content, but missed the target by contract completion: what is the required procedure?

The issue
A bidder wins after proposing a high local content percentage that improves its evaluation. During delivery or at contract completion, it becomes clear the committed percentage has not been met. This may undermine the entity’s local content objectives and requires action under the applicable rules.
Worked example
Contract value: SAR 20 million. Target: 45%. Achieved: 35%. Shortfall: 10 percentage points.
Can this be detected during qualification?
Partly. Qualification checks capabilities, resources and relevant experience. Actual achievement can only be established by monitoring delivery and results.
Verification and action at each stage
1. Prequalification: assess capabilities and resources against the specified criteria.
2. Bid evaluation: verify the target percentage and request clarifications. If insufficient, exclusion may be considered in coordination with the Local Content and Government Procurement Authority, as applicable.
3. Contract delivery: follow the gradual plan within 60 days of award, review periodic reports and address shortfalls against the target.
Actions by size of shortfall
5 percentage points or less: Article 31 target shortfall penalty does not apply. Other obligations continue.
More than 5 through 15 percentage points: Article 31 penalty, normally capped at 10% of contract value, calculated under the tender documents.
More than 15 percentage points: apply the penalty and refer the matter under Article 37 to the competent committee to consider a ban on government contracting, a classification reduction where applicable, or both.
Late or missing final report: Article 32 penalty normally capped at 10% of contract value, calculated under the tender documents. Article 37 also provides for referral for failure to submit within the deadline.
Apply to the example
45% minus 35% = 10 percentage points. Apply Article 31 as set out in the tender documents. The ordinary maximum is SAR 2,000,000 (10% of SAR 20 million). This is a ceiling; the actual amount depends on the applicable contractual formula.
Six practical lessons
Verify local content requirements before award. Follow the gradual plan within 60 days. Review periodic reports throughout delivery. Address deviations early. Document achieved percentages and actions. Apply penalties under the regulation and tender documents.
Takeaway
Local content is a contractual commitment that must be monitored and verified, with the applicable remedies used when obligations are breached. Educational content and independent professional judgement. Prepared by Ibrahim Alhumaid.
References: Articles 20, 21, 31, 32, 33 and 37 of the Local Content Preference Regulation.