Substituting a Material or Product During Contract Performance

Decision paths: from the substitution request to installation or a final decision.

Main route: request before installation

  1. Submit a substitution request. The contractor provides the reasons, specifications and proposed alternative in writing.
  2. Assess technical conformity. The consultant or technical team checks the alternative against the specifications and requirements.
  3. Review the contract. The government entity checks whether the alternative meets the contract terms and specifications.
  4. Assess the impact. Consider price, schedule, warranties and other obligations.
  5. Obtain the required approval. Approve a conforming alternative where permitted. If the proposal changes contractual terms, determine whether an authorized change order or another formal contractual procedure is required.
  6. Implement and accept. Supply the approved alternative, verify conformity and document acceptance.

Decision branches

A. The contractor asks before installation

  • Conforming and no contractual change: Approve the alternative through the prescribed process before installation.
  • Conforming but price, schedule or obligations change: Assess the legal basis and route the required formal approval or change order to the authorized official before proceeding.
  • Not approved: If the alternative fails the specifications, has an unacceptable financial impact or conflicts with contract requirements, continue with the original product under the contract.

B. The entity discovers an unapproved installation

Document the installation and assess technical, contractual and financial impacts before deciding on acceptance.

  • Product meets the specifications: Check any financial impact and refer the case for a documented decision. Consider any later approval or change order only if a legal and contractual basis supports it. Conformity does not automatically cure missing approval or justify backdating.
  • Product does not conform or breaches the contract: Use the contract’s remedies, which may include requiring removal and replacement with an approved product, allocating the contractor’s costs where justified and applying penalties if applicable.

Who does what?

Regulatory references

These references concern Royal Decree M/128 and its implementing regulations. Check the transitional rules and the individual contract.

Law and regulations · Article 114 amendment · Official Gazette: transitional provisions

Bottom line