Procurement and Committee Scenarios and Solutions

Before tendering, during bid evaluation and throughout the contract
When a decision is difficult
- Several options may carry different legal, financial or operational consequences. The difficulty may come from interpreting a rule, conflicting views, time pressure or unclear responsibilities. Decide whether to proceed, pause, seek a legal opinion, or escalate to the authorized decision-maker.
Before issuing the tender
- 1. Urgent purchase. The requesting department wants a fast contract. Verify the grounds for urgency and select the proper procurement method. Urgency alone does not justify bypassing competition.
- 2. Product-specific specifications. Review the technical requirements and their justification with the requesting department. Check whether they restrict competition without a lawful basis.
- 3. A recurring need. Analyze expected demand and choose a suitable contracting method. Avoid splitting purchases to circumvent procurement rules.
- 4. Unclear estimated cost. Complete the market study and verify the basis for the estimate before proceeding.
During tendering and bid evaluation
- 5. Error in published tender documents. Assess the impact on competition and equal opportunity. Determine whether correction, a deadline extension or another action is required at the current stage.
- 6. Only one bid received. Check the specific rules for single bids and obtain the necessary approvals before accepting or deciding to reissue the tender.
- 7. Abnormally low bid. Refer it for the applicable low-bid review to assess the seriousness of the bid and the bidder’s ability to perform.
- 8. Committee members disagree on technical scoring. Apply the approved criteria and document the views while respecting the committee’s independence and remit.
- 9. Bid validity expires before award. Check the applicable rules on validity and extensions before continuing.
After award and during performance
- 10. Supplier delays signing. Check notices, formal warnings and statutory deadlines before recommending whether to wait or proceed to the next step.
- 11. Request to add work. Check scope, the type of increase, applicable limits and requirements, and contractor consent when required. Determine whether to issue a change order or contract separately.
- 12. Contractor requests a price adjustment. Verify applicable statutory grounds, evidence and supporting documents, then refer the claim for the prescribed review.
- 13. Contractor struggles to perform. Identify the cause and respective responsibilities. Check contract provisions, notices, penalties and approval powers before deciding on sanctions, extension or withdrawal of work.
- 14. Contract nears expiry but the need continues. Check extension conditions and permitted grounds. Start planning early for a replacement tender if needed.
- 15. Requesting department and procurement disagree. Distinguish technical responsibility, contracting process and approval authority. Document the disagreement and refer it to the appropriate decision-makers.
Five situations for professional discussion
- A significant error appears after bids are opened. Assess how it affects fairness, document the impact, seek the appropriate opinion and select the legally available action.
- The lowest bid concerns the committee. Apply the low-bid review rules, request clarification and rely on the review results as well as price.
- Additional work is requested mid-contract. Check its nature and whether it is a new requirement. Observe limits and obtain approvals before work begins.
- The requesting department asks to exclude a bidder. Distinguish technical advice from the bid evaluation committee’s remit. Apply the criteria, document the concern and refer it for decision.
- Someone asks to accelerate the process by cutting review. Check delegated powers and remove unnecessary steps while preserving legal requirements and mandatory controls.
Six steps for a decision
- 1. Define the decision required. 2. Gather facts and documents. 3. Check the law, regulations and contract. 4. Identify who examines, recommends and approves. 5. Compare the legal, financial and operational effects of each option. 6. Document the basis for the recommendation and final decision.
Build an internal case register
- Record the issue, governing provisions, responsible unit or decision-maker, approved recommendation or action, steps followed, and improvements to prevent recurrence.
- Use the register as a living internal reference alongside applicable rules and legal advice. Verify the basis, authority and impact of the decision. Find the shortest lawful path that protects both the decision and operational efficiency.