Can a contractor replace key personnel without the entity’s approval?

When may a replacement be accepted, and when does it breach the contract?
Approval of key personnel carries contractual obligations. If the contract requires approval for changes, the contractor must follow that requirement and propose a replacement with the required qualifications.
When may a replacement be accepted?
- A team member resigns or is unable to continue.
- The contractor submits a formal request with reasons.
- The replacement meets the qualification and experience requirements.
- The entity approves the replacement before the person starts work.
When is a change impermissible?
- The contractor makes the replacement without the entity’s approval.
- The replacement has less experience than required.
- The change breaches the contract’s staffing requirements.
- The replacement starts work before approval.
What is the correct procedure?
- Submit a formal request to replace the team member.
- Attach the reasons for the request and the proposed replacement’s CV.
- Review the qualifications and experience.
- Approve the replacement before work begins.
Summary
If the contract requires the entity’s approval to replace key personnel, the contractor must obtain that approval and provide a replacement who meets the required qualifications before the replacement starts work.
Legal references
- Tender documents.
- The approved contract.
- Special conditions governing key personnel.