Retroactive Actions in Government Procurement and Contracts
When can an error be corrected, and when is late approval not enough?
A tender is launched before a required approval is in place. Work starts before a decision is issued. Additional works are carried out before a change order. Which of these errors can be corrected later?
Six stages, six common errors
1. Preparing and launching the tender
What went wrong: The entity launches a tender before securing a required approval, such as budget authorization or technical clearance.
Suggested corrective action: Identify the missing approval and assess whether its absence affects the validity of the launch. Obtain it if the applicable rules allow correction at that stage; otherwise refer the question of continuing the tender to the authorized official.
2. Opening bids
What went wrong: Bids are opened before the decision establishing the bid-opening committee is issued.
Suggested corrective action: Record what happened. Verify the integrity and confidentiality of the bids and determine whether the procedure can lawfully be corrected. If it cannot, examine cancellation under the applicable rules.
3. Evaluating bids
What went wrong: A report or recommendation is prepared before the bid evaluation committee is established.
Suggested corrective action: Form the committee lawfully. Have it undertake an independent review of the bids and technical reports and issue its own documented recommendation.
4. Award
What went wrong: A bidder is instructed to start work or mobilize before the award decision is issued.
Suggested corrective action: Stop instructions that lack authority and record the facts. Complete the award and contracting steps in the required order, without treating a later decision as authorization for earlier work.
5. Contracting
What went wrong: Services or works begin before the contract has been duly concluded, whether through a formal agreement or authorized correspondence where permitted.
Suggested corrective action: Identify the actual basis on which work began and document what was performed. Refer the breach and any financial or contractual consequences to the competent functions for review.
6. Change request and order
What went wrong: Extra work is performed before the authorized official issues the change order.
Suggested corrective action: Document the work and instructions. Verify necessity, scope, funding and authority; assess responsibility and any claims without assuming that a later order makes the work valid retroactively.
Why these errors happen
- Rushing to complete a tender.
- Weak planning.
- Unclear authority and responsibilities.
- Delays in establishing committees.
- Poor coordination between departments.
- Pressure from deadlines and budget allocations.
- Reliance on undocumented verbal instructions.
Three ways to classify the issue
- Complete the record
- A lawful step was taken on time, but its proof or supporting documents were added later. Record the actual dates.
- Correct a remediable procedure
- A procedural error may be corrected where the rules allow and where the correction preserves fair competition and the parties’ rights. Verify this before proceeding.
- Do not assume retroactive validity
- A late decision does not make an earlier action lawful if requirements were missing at the time, unless an express legal basis permits that remedy.
Legal references
Article numbers refer to the Saudi Government Tenders and Procurement Law issued under Royal Decree M/128. Check the tender date and transitional provisions to identify which rules govern a particular case.
- Law, Articles 43 and 45: Establishment of the bid-opening and bid evaluation committees; Article 45 also addresses the latter’s role in reviewing bids and making recommendations.
- Law, Article 51: Tender cancellation where a breach of the law or regulations cannot be corrected.
- Law, Article 53: Standstill after award announcement, before award approval and contract signing.
- Law, Article 54: Authority to decide tenders and assign additional work.
- Law, Article 59: Contract formalities and commencement in public construction. See also amended Implementing Regulations Article 88(5) on the restriction against commencing before conclusion of the contract, subject to Law Article 55(2).
- Law, Article 69 and amended Implementing Regulations Article 114: Changes that increase or reduce contractual work, and the applicable conditions and authority.
Ministry of Finance: law and regulations · Ministerial Decision 1097: amended regulations · Official Gazette: transitional provisions
Bottom line
A late decision does not automatically validate a prior action. Record what took place and when, identify the nature of the breach, and choose the remedy the applicable rules permit.
View the signed Arabic infographic