Supplier Performance Evaluation After Contract Signing: Criteria and Weights by Contract Type

↓ Download
Supplier Performance Evaluation After Contract Signing: Criteria and Weights by Contract Type. An accessible transcript follows.

English transcript

Purpose

Contractor performance evaluation criteria and weights differ according to Ministry of Finance official models and contract type to measure how far value and the return on contracting are achieved. The following weights reproduce the examples from the Arabic design.

Supply contracts

Material quality and conformity with specifications 30%; adherence to delivery schedules 25%; contractual compliance 15%; quantity accuracy and packaging condition 10%; after-sales service 10%; risk management 5%; local content 5%. Total 100%.

Consulting services contracts

Quality of study and deliverables 30%; timeliness 20%; staff expertise and methodology 15%; contractual compliance 15%; knowledge transfer and capacity building 10%; risk management 5%; local content 5%. Total 100%.

Technical services contracts (information technology)

Quality of deliverables and services 25%; adherence to timelines and project stages 20%; change management and support 15%; contractual compliance 15%; risk management and cybersecurity 10%; operational efficiency 10%; local content 5%. Total 100%.

Operation and maintenance contracts

Quality of execution and works 25%; timeliness 20%; response to maintenance reports 15%; contractual compliance 15%; risk management 10%; operational efficiency 10%; local content 5%. Total 100%.

Pharmaceutical and medical supplies contracts

Product quality and regulatory compliance 30%; adherence to delivery schedules 25%; storage and transportation safety 15%; contractual compliance 10%; after-sales service 10%; risk management 5%; local content 5%. Total 100%.

Engineering services contracts (design/supervision)

Design/supervision quality 30%; timeliness 20%; technical staff experience 15%; contractual compliance 15%; safety and quality 10%; risk management 5%; local content 5%. Total 100%.

Road construction contracts

Execution quality and specifications 30%; timeliness 25%; road safety 15%; contractual compliance 10%; risk management 10%; environmental and community impact 5%; local content 5%. Total 100%.

General construction contracts

Execution quality and conformity with specifications 30%; compliance with timeline and work schedule 25%; occupational health and safety 15%; contractual compliance 10%; risk management 10%; resource and site management 5%; local content 5%. Total 100%.

Supplier performance evaluation steps

1. Define evaluation criteria and weights by contract type. 2. Gather data and evidence periodically. 3. Conduct evaluation according to the official model. 4. Discuss results with supplier and establish an improvement plan. 5. Use evaluation results in future decisions.

Expected outcomes

Achieve contracting value and return. Increase compliance and implementation quality. Reduce risks and challenges. Improve future procurement decisions. Strengthen transparency and governance.

Important notes

Percentages and weights vary according to the official model and contract type. Some models may include additional criteria depending on project nature. Use the model approved by the Ministry of Finance and Etimad when carrying out actual assessments. The entity may adjust weights to suit the specific contract within applicable statutory controls.