Can contractors suspend work if a government entity delays payment?

When can contractors make a claim, and when may they not suspend work?
Late payment gives the contractor no automatic right to suspend work. The contractor may claim amounts due and seek a remedy, an extension, or compensation where the applicable legal conditions are met.
When may the contractor make a claim?
- The amounts due have been approved but remain unpaid.
- The government entity is shown to have caused the delay.
- The delay has had an actual impact on performance.
- The contractor meets the conditions for a claim, contract extension, or compensation.
When is suspension impermissible?
- The contractor stops work unilaterally without a valid basis.
- The contract does not provide for suspension.
- The effect of the delay on performance has not been established.
- The contractor disregards the applicable procedures and formal notices.
What is the correct procedure?
- Submit a formal claim for the amounts due.
- Document the delay and its impact on performance.
- Request a remedy, extension, or compensation as appropriate.
- Continue performing under the contract unless there is a legal basis for suspension.
Summary
Late payment gives the contractor no automatic right to suspend work. The contractor may claim amounts due and seek a remedy, an extension, or compensation where the applicable legal conditions are met.
Legal references
- Government Tenders and Procurement Law of 1440 AH: Article 67 (payment of contractor entitlements) and Article 74 (contract extensions).
- Relevant provisions of the Implementing Regulations and the contract.