Committees
The technical department recommends exclusion, but the bid evaluation committee finds the bid compliant: who decides?

The technical department provides evidence-based specialist advice; the bid evaluation committee reviews bids and prepares its recommendation under the published criteria and applicable rules. The competent authority makes the award decision.
Practical case
A government entity invites bids to supply and operate technical equipment. Estimated value: SAR 12 million.
Bid 1: SAR 9 million; Bid 2: SAR 10.5 million; Bid 3: SAR 11 million.
The technical department recommends excluding Bid 1 because a device does not meet a technical requirement in the tender documents. The committee considers its performance equivalent and believes the difference may not affect actual use.
What is the issue?
Can the committee accept the bid despite the technical department’s recommendation?
Is the discrepancy material, or may it be accepted under the tender rules?
Would accepting the alternative give the bidder an advantage not offered to others?
Who bears responsibility if the device is later found noncompliant?
Legal basis
Law Article 45: the bid evaluation committee examines bids and recommends the best bid against the published evaluation criteria.
Regulations Article 74: committee membership includes a member with relevant technical knowledge.
Regulations Article 75: the committee must follow qualification and evaluation criteria and tender conditions.
Regulations Article 79: distinguishes minor deviations that may be accepted under applicable conditions from material deviations requiring exclusion.
How to resolve disagreement
1. Material technical deviation: if a mandatory, material specification is unmet, apply exclusion rules and document the noncompliance.
2. Minor technical deviation: assess impact on specifications, cost and fairness of comparison; determine whether acceptance is permitted.
3. Ambiguous bid: request written clarification without allowing substantive changes or converting a noncompliant bid into a compliant one.
4. Persistent disagreement: request documented technical analysis identifying the disputed specification and grounds for acceptance or rejection; submit the recommendation to the competent authority.
Six practical lessons
Define mandatory specifications and alternative acceptance criteria clearly.
Link each technical observation to a specific clause.
Request evidence proving compliance or noncompliance.
Distinguish a product description difference from failure to meet essential requirements.
Document reasons for acceptance or recommended exclusion.
Maintain independent technical evaluation and fair comparison among bidders.
Most important lesson
Resolve technical disputes through clear specifications, accurate evidence and documented reasons. A sound award rests on compliance and fair evaluation, not price alone.
Key takeaway
The technical department provides evidence-based specialist advice. The committee is responsible for bid evaluation and recommendations according to the applicable criteria and conditions; the competent authority decides the award.