Tenders
How to Choose the Right Time to Issue a Tender

The planning decision
Set the issue date by considering when the need is confirmed, the scope and specifications are complete, approvals are in place, the market is ready and delivery must begin. A date in the annual procurement plan or the availability of funds alone cannot establish readiness. Allow enough time to complete the procurement process and sign the contract before the service is needed.
1. What should you check before issuing the tender?
- Need: Has the requesting department clearly defined and approved the need?
- Specifications: Are the scope of work, tender documents and technical requirements ready?
- Financial estimate: Have you reviewed market prices, estimated the cost and secured the necessary financial approvals?
- Procurement lead time: Have you allowed time for publication, enquiries, bid evaluation, award and contracting?
- Market readiness: Does the timing suit the work and the capacity of potential suppliers?
- Seasons and holidays: Could seasonal conditions affect supplier participation or delivery?
- Mobilisation: How much time does the incoming contractor need to assemble resources before the service starts?
- Existing contracts: Have you scheduled the replacement tender sufficiently far ahead of the current contract’s expiry?
2. Contracts for ongoing services
Maintenance, cleaning, operations, technical support, hosting and technical services may be needed continuously. Set an early issue date for the replacement tender. Work back through document preparation, approvals, publication, bid evaluation, award, signing and mobilisation of the incoming contractor.
Plan the handover of work, knowledge, data and equipment between contractors. The new service should begin as the current contract ends, with a smooth transition and no interruption.
3. How to set the issue date
- Identify the date the service is actually needed.
- Work backwards from that date.
- Allow time for review and approval.
- Build in time for risks and possible delays.
- Approve the issue date and monitor progress against it.
4. Signs of poor timing
- Few suppliers participate or submit bids.
- Unclear requirements generate many enquiries.
- The bid submission deadline is extended repeatedly.
- Award or contract signing is delayed.
- The contractor is unprepared to begin work.
- The current contract expires before its replacement begins.
- Services are interrupted or temporary arrangements become necessary.
5. Benefits of early planning
- Tenders are better prepared before issue.
- Suppliers have enough time to prepare bids.
- Departments plan and coordinate more effectively.
- Award and signing delays become less likely.
- The contractor is better prepared to start.
- Essential services continue.
- Gaps between successive contracts become less likely.
- Projects and services can start on the required dates.
Summary
Start with the date the need arises and work backwards through preparation, tendering, award, signing, mobilisation and delivery. For ongoing services, begin planning the replacement well before expiry. The aim is a contract ready to deliver on time, uninterrupted service and compliance with applicable procedures and regulations.