Government Tender Timelines: From Tender Documents to Contract Signing

English transcript
According to the Government Tenders and Procurement Law and its Implementing Regulations
The original table presents tender method, statutory references, estimated value, publication/submission time, estimated-values time (as labeled in the source), examination and evaluation, award approval, standstill under Article 87, contracting and signing under Article 88, and total target in working days. Ranges below follow the original source; they are planning estimates except for explicitly identified statutory periods.
01 | Public tender (small)
Law: Articles 28 and 29; Regulations: Article 34. Estimated value: up to SAR 5 million. Publication/submission: 15 calendar days (11 working days for comparison). Estimated-values stage: 3–5 days; examination/evaluation: 3–5 days; award approval: 5–10 days; standstill: 5–10 days; contracting/signing: 5–10 days. Target total: 34–56 working days.
02 | Public tender (medium)
Law: Articles 28 and 29; Regulations: Article 34. Estimated value: more than SAR 5 million and less than SAR 100 million. Publication/submission: 30 calendar days (22 working days for comparison). Estimated-values stage: 10–15 days; examination/evaluation: 10–15 days; award approval: 5–10 days; standstill: 5–10 days; contracting/signing: 5–10 days. Target total: 50–74 working days.
03 | Public tender (large)
Law: Articles 28 and 29; Regulations: Article 34. Estimated value: SAR 100 million or more. Publication/submission: 60 calendar days (43 working days for comparison). Estimated-values stage: 15–25 days; examination/evaluation: 15–25 days; award approval: 5–10 days; standstill: 5–10 days; contracting/signing: 10–15 days. Target total: 83–113 working days.
04 | Limited tender
Law: Article 30; Regulations: Articles 35–39. Estimated value and publication/submission: according to invitation. Estimated-values stage, examination/evaluation, award approval, standstill and contracting/signing: 5–10 days each. Target total: 23–45 working days.
05 | Direct purchasing
Law: Article 32; Regulations: Articles 40–45 in the main table. Estimated value: statutory provisions and applicable cases. Submission: 1–1 days; estimated-values stage: 1–3 days; examination/evaluation: 3–3 days; award approval: not applicable; standstill: 1–3 days; contracting/signing: 1–3 days. Target total: 8–18 working days.
06 | Two-stage tender
Law: Article 31; Regulations: Articles 46–49. Estimated value: according to project nature. Publication/submission: 10–30 days. Estimated-values stage, examination/evaluation, award approval, standstill and contracting/signing: 5–10 days each. Target total: 40–85 working days.
07 | Framework agreement (establishment)
Law: Article 33; Regulations: Articles 50–55. Estimated value: according to launch method. Publication/submission: 5–15 days. Estimated-values stage, examination/evaluation, award approval, standstill and contracting/signing: 5–10 days each. Target total: 28–62 working days.
08 | Framework agreement (purchase order)
Law: Article 33; Regulations: Articles 56–59. Estimated value: according to agreement. Publication/submission: 3 days; estimated-values stage: 3 days; examination/evaluation: 3 days; award approval: not applicable; standstill: 1–3 days; contracting/signing: 1–3 days. Target total: 4–14 working days.
Tender stages
1. Upload documents and publish the tender (according to tender type and value). 2. Submit bids (Article 34). 3. Examine and evaluate. 4. Approve award. 5. Standstill (Article 87). 6. Complete guarantee and approvals. 7. Contract and sign (Article 88).
Key statutory references listed in the source
Public tender: Law 28, 29; Regulations 34. Limited tender: Law 30; Regulations 35–39. Direct purchasing: Law 32; the reference summary box appears to read 40–40, while the main table states Regulations 40–45. Two-stage: Law 31; Regulations 46–49. Framework agreement (establishment): Law 33; Regulations 50–55. Framework agreement (purchase order): Law 33; Regulations 56–59. Standstill: Regulations 87. Contract conclusion and signing: Regulations 88. Article ranges are transcribed from the infographic; consult the official regulations rather than treating these ranges as a definitive index.
Important notices
The original bid submission periods are 15, 30 and 60 calendar days under Article 34 of the Implementing Regulations for public tenders; figures in parentheses (11, 22 and 43 working days) are for planning and comparison. Standstill ranges from 5 to 10 working days under Article 87. Examination/evaluation, award approval, completion of guarantees and contracting/signing durations are proposed operational planning targets based on government entity practice and expenditure efficiency authority guidelines. The total varies with project nature, procedures and required approvals. The table uses working days for operational planning and service-level agreements (SLAs) and is subject to applicable statutory procedures and approvals.
Practical application
These durations help government entities build an SLA, determine and evaluate tender times, monitor adherence and improve procedural efficiency. The original table contains some internal inconsistencies between stage durations and total targets; its figures are reproduced as shown rather than silently recalculated. Verification note: Article 34 confirms the 15, 30 and 60-day minimum periods, subject to a permitted ministerial reduction; Law Article 53 and Regulations Article 87 require a 5–10 working-day standstill after announcement of the award decision, during which award approval and signing may not occur. The source's operational sequence must be interpreted subject to that statutory requirement.
Reference note
English edition of the Arabic educational infographic. Unless explicitly identified as verified, legal citations and figures are those of the original source and may reflect its publication date. Check the applicable official text and transitional provisions before relying on them.