A delayed tender
The tender is 20 days behind schedule. The documents have been returned three times. The team proposes adding reviewers. What do you do first?
All three reviews flag the same technical requirement. Bring the requesting unit and technical team together to resolve it, then assign someone to check it before submission.
In this case the next review finishes sooner, but the new reviewer returns the documents over the same requirement. Compare the comments and identify the missing information.
The longer schedule allows more time, but the team repeats the same discussion. Review the reasons for rework before revising other tender schedules.
A committee member’s prior relationship
Before bids are scored, a committee member recognizes a former business partner among the bidders. How should the member handle that relationship?
A colleague knows about the relationship, but the evaluation record contains no decision about the member’s role. Submit the disclosure for assessment and documentation.
The authority can assess the relationship, define the member’s role and record its decision before scoring begins. Monitor changes that might affect impartiality.
By the time an objection is raised, the member has already scored the bids. The authority may need to review the effect of that participation. Early disclosure allows a timely decision.
The approved model is unavailable
A supplier says the manufacturer has discontinued the approved model and offers a more expensive replacement. What do you request before a decision?
The substitute arrives before equivalence, price fairness and approval have been established. Check the specifications, financial impact and authority before instructing delivery.
The price difference identifies a cost impact. Suitability and the reason for substitution still need examination. Request evidence and a comparison to assess the options.
The team can now assess the reason for substitution, technical equivalence and the basis for the price difference. Record the recommendation and seek approval under the contract before implementation.