Ibrahim Alhumaid
Back to categories · العربية

When the approved model cannot be supplied in a government contract

Try the case in the Decision Lab

↓ Download
When the approved model cannot be supplied in a government contract. An accessible transcript follows.

Can a substitute be accepted, and how should the price difference be handled? Practical cases, acceptance criteria, and the role of procurement and contracts.

1. Supply becomes impossible for reasons beyond the supplier’s control

The entity may approve an equivalent or better substitute.

Same price: no adjustment. Lower price: use the lower price. Higher price: assess and approve the difference under the applicable rules.

Obtain a reasoned request from the supplier, conduct a technical review, and secure prior approval from the entity.

2. The entity seeks better specifications or a different model

An amendment is permissible if it remains within the contract scope and does not result in a material change.

Reprice the difference using agreed or prevailing prices.

Prepare a contractual change order after review and approval.

3. The model is unavailable because the manufacturer discontinued it

An equivalent substitute may be accepted on the basis of an approved technical recommendation.

Use the substitute’s actual price, higher or lower, after verifying that it is fair.

Update the specifications and approve the contract amendment.

4. The supplier seeks substitution without a valid reason

The substitution is impermissible and constitutes a breach of contract.

No price adjustment is accepted.

Reject the request and apply the remedies specified in the contract.

Regulatory requirements

Comply with the contract, the Government Tenders and Procurement Law, and its Implementing Regulations.

Do not materially change the contract’s scope or subject matter.

An amendment requires a valid reason and approval from the competent authority.

Acceptance criteria

The substitute must be equivalent or better in specifications and performance, approved by the competent technical authority, and consistent with technical and safety requirements.

It must preserve the nature and purpose of the contract and be appropriate in cost and value.

Role of procurement and contracts

Review the request and technical assessment with the beneficiary department.

Verify the reasons for substitution and the fairness of the price.

Document the amendment in the contract and its annexes.

Monitor the effect on contract cost and duration.

Bottom line

A substitute model can be accepted under defined conditions following a technical assessment and formal approval. Handle the price difference according to the circumstances of each contract.